Energy Affordability Act (H 5484, SC)
Last Updated:
Bill Status
Summary:
Requires electric utilities to develop contract and other terms to ensure data centers cover all costs due to them, including by: minimum contract terms and billing requirements, termination requirements and collateral. Contract subject to Public Service Commission approval. Data centers required to report water usage to Department of Environmental Services monthly, and anticipated usage prior to commencing operations. Data centers required to file decommissioning plans and financial assurance for costs. Ends certain tax breaks for data centers; makes one contingent on fee-in-lieu agreement.
Session:
Current
State / Federal:
Bill Number:
H 5484
Party of sponsors/cosponsors:
D
Concerns, objectives, methods:
rates, capacity, regulation, study/data collection, incentive-
Compare to other policy:
Search the tracker for other policy related to this gateway →